Following is a likely timeline for development of Measure C:
 
July 2003 CCTA approved 3 alternative plans for study
Jan - Feb 2004 Public comment on 3 alternative plans
March-April 2004 CCTA proposes Draft, then Final Measure C plan
May 2004 CCTA adopts Final Measure C plan

June-July 2004

Final Measure C plan submitted to Cities & County for resolutions of support

Aug 6, 2004

Last day for Board of Supervisors to put Measure C on the ballot

Nov 2, 2004

Election day

For a more detailed schedule of CCTA meetings, see http://www.ccta.net/EXTENSION/2004wkshp/wkshpsched.pdf